SPC Flooring Lead Time: What Importers Should Plan for, From Deposit to Delivery

Wednesday, 04/11/2026 0

Ask three suppliers for their SPC flooring lead time and you may get three different answers. One counts the days of production. Another counts the time until the container leaves the port. A third counts the time until the goods reach your warehouse.

For an importer, that difference decides when you can start selling, how much stock you carry and how costly a delay becomes. A lead time is only useful when you know where the clock starts, what it covers and what happens after it stops.

This guide breaks the timeline into its stages, explains what ATT Floor's seven-day production figure does and does not cover, and shows how to plan your own total lead time.

Let's take a closer look with ATT Floor.


1. Three Meanings of Lead Time

Before comparing numbers, compare definitions.

Term

What it measures

Who it matters to

Production lead time

From the start of the clock (usually the deposit) until the goods are finished

Factory and buyer

Order lead time

From the deposit until the container is loaded and handed over at the port of shipment

Buyer planning shipments

Total lead time

From the deposit until the goods are in your warehouse

Buyer planning stock and sales

A supplier who quotes a production time is not wrong, but that number cannot be compared with another supplier's total lead time.

Under FOB Hai Phong, ATT Floor's part ends when the goods are loaded on board at the port. Ocean freight, customs clearance and delivery to your warehouse are arranged on your side.

SPC flooring production line at the ATT Floor factory in Ninh Binh

                                                                   SPC flooring production line at the ATT Floor factory in Ninh Binh


2. The Stages Between Deposit and Delivery

A typical SPC flooring order moves through eight stages. Stages 1 and 2 take place before the production clock starts.

Timeline of the eight stages from specification approval to inland delivery

                                                             Timeline of the eight stages from specification approval to inland delivery

Stages 6 to 8 depend on your route, so no factory can give you one figure for them. Ask your forwarder for current estimates for your port.

For the full import process, see How to Import SPC Flooring from Vietnam. For stage 4, use the SPC flooring quality control checklist.


3. What Seven Days After Deposit Means at ATT Floor

ATT Floor promotes production completion within seven days after the deposit. The figure is specific, so the conditions matter.

3.1. When the Clock Starts

The clock starts after ATT Floor receives the deposit. Specification, samples and approvals are completed before that point. Treat any change to the specification or the artwork after the deposit as a new conversation about timing.

3.2. What It Covers

For available specifications and decors, ATT Floor works to complete production within seven days after receiving the deposit, subject to factory confirmation.

3.3. What It Does Not Cover

  • Ocean freight, customs clearance and delivery. These stages come after production.
  • Customized decors. They are scheduled per project and do not automatically follow the seven-day figure.
  • A per-container guarantee. The seven days is a production milestone for available specifications and decors, not a promise for every container in a larger program. For larger or mixed orders, ask for the factory's confirmed schedule.

Finished SPC flooring cartons stacked on pallets, ready for loading

                                                          Finished SPC flooring cartons stacked on pallets, ready for loading


4. Available Decors vs Customized Decors

With available specifications and decors, the decision is simple: confirm the specification, pay the deposit, and production follows the schedule above.

Customized decors add steps before the order. You provide a reference, the factory works on color matching, and you approve a sample. Production for customized decors is then scheduled per project.

The practical rule is to settle the decor, the sample and the packaging artwork before the deposit. If you are still deciding on thickness and wear layer, start with How to Choose SPC Flooring Specifications for Your Market.


5. How to Read Any Supplier's Lead-Time Promise

Ask these six questions before you compare two suppliers:

  1. When does the clock start? The deposit, the purchase order or the artwork approval?
  2. What does the number cover? Production only, loading, or delivery to your port?
  3. Which products qualify? Available specifications only, or custom decors too?
  4. Does it apply per order or per container?
  5. Who arranges each stage after production under the agreed Incoterm?
  6. What is the plan if the date slips?

A supplier who can answer all six clearly is giving you a lead time you can plan around. A quotation that says only that lead time is on request, or gives one number with no conditions, needs a follow-up question before you compare it.


6. Planning Your Own Total Lead Time

The supplier's production time is one input. Your own planning needs the total, from the deposit to your warehouse, and a safety margin.

A simple reorder formula:

Reorder point = average weekly sales x total lead time in weeks + safety stock

Example, for illustration only:

Item

Example value

Average weekly sales

1,000 m²

Total lead time, deposit to warehouse

10 weeks

Safety stock

3 weeks of sales = 3,000 m²

Reorder point

1,000 x 10 + 3,000 = 13,000 m²

These figures are placeholders for your own data. They are not an ATT Floor quotation or a typical transit time. Use the lead times your supplier and your forwarder confirm.

Because the standard MOQ is one full container, each order is also a stock-planning decision. The SPC flooring container loading guide explains how specifications affect the quantity per container.

6.1. Produce Now, Ship Later

ATT Floor offers a Produce Now, Ship Later option. Production is completed ahead of shipment, and the cargo ships when ocean freight is more favorable. Storage terms are agreed in advance.

This separates production time from shipping time, so you can plan the shipping window around freight rates. Agree the storage period and conditions with the supplier before the deposit.

SPC flooring containers being loaded for export

                                                                            SPC flooring containers being loaded for export


7. Common Lead-Time Mistakes

  • Comparing a production time with a total lead time. The two numbers measure different things.
  • Starting the clock before the specification is final. Approvals belong before the deposit.
  • Changing specification or artwork after the deposit. It puts the schedule at risk.
  • Planning only the factory stage. Ocean freight, customs and delivery take time too.
  • Mixing too many colors and thicknesses in the first container. The standard structure is two to three colors and one thickness per container.
  • Carrying no safety stock. One late vessel should not empty your shelves.

8. How ATT Floor Handles Lead Time

ATT Floor is a Vietnam-based manufacturer specializing in SPC rigid-core click flooring, with production in Ninh Binh. The standard basis is FOB Hai Phong, and quotations and freight validity are set per project. The standard MOQ is one full container. For available specifications and decors, ATT Floor works to complete production within seven days after receiving the deposit, subject to factory confirmation. Customized decors are scheduled per project. Test reports and certification documents are available on request.

Planning an order? Send us your target market, thickness, wear layer, preferred colors or decors and the date you need the goods in your warehouse. We will confirm what is feasible and come back with a specification-based proposal. WhatsApp / tom@attfloors.com

Export Sales Executive: Tom Nguyen

You can also see the SPC Click Flooring range and read how a plank is made in SPC Flooring Factory in Vietnam: Inside the Manufacturing Process.


9. Frequently Asked Questions

9.1. What is the lead time for SPC flooring?

It depends on what the supplier counts. At ATT Floor, production for available specifications and decors is promoted as complete within seven days after the deposit, subject to factory confirmation. Ocean freight, customs and delivery are additional.


9.2. How long does it take to import SPC flooring from Vietnam?

The total is the sum of production, loading, ocean freight, customs clearance and delivery, and the last three depend on your route. Ask your forwarder for current estimates for your port. Under FOB, ATT Floor's part ends when the goods are loaded on board at Hai Phong.


9.3. When does the production clock start?

It starts after ATT Floor receives the deposit. Specification, samples and approvals are completed before that point.


9.4. Does the seven-day figure apply to customized decors?

Not automatically. Customized decors are scheduled per project, after the reference, color matching and sample approval steps.


9.5. Can ATT Floor produce early and ship later?

Yes. The Produce Now, Ship Later option completes production ahead of shipment so the cargo can ship when ocean freight is more favorable. Storage terms are agreed in advance.


9.6. Which port do you ship from?

The standard basis is FOB Hai Phong. Quotations and freight validity are set per project.


9.7. What is the MOQ for an SPC flooring order?

The standard MOQ is one full container, normally with two to three colors and one flooring thickness per container.


10. Final Thoughts

A lead time is a promise only when its conditions are clear. Know where the clock starts, what the number covers and who arranges each stage after production, and you can compare suppliers fairly and plan your stock with confidence.

If you are planning your next SPC flooring order, send us the specification and the date you need the goods, and we will confirm what is feasible before you commit to a container.


You can refer to SPC Flooring Container Loading Guide: How Specifications Affect Quantity, Weight and Landed Cost

Manufacturing Factory 1: Km7, Ha Nam Ward, Ninh Binh Province, Vietnam
Manufacturing Factory 2: Kim Binh Cluster, Ha Nam Ward, Ninh Binh Province, Vietnam
Manufacturing Factory 3: Lot CN-1.7, Le Ho Industrial Cluster, Le Ho Ward, Ninh Binh

Phone/WsA: +84 915961582

Email: tom@attfloors.com

Call us now
whatsapp Chat with us on Whatsapp
Send us an email
Contact